Quality Control & Report Creation: Concrete

1.From Home, navigate to Quality Control > Concrete / Grout / Mortar. If necessary, use the Change Project button to change to the project used in the Field module.
2.

Select the Concrete tab.

3.Remove all filters from the filter panel and select the Filter button control. You should see concrete samples from earlier exercises. If not, use the Change Project button control to find a project with test data.
4.

In the filter pane, check Analyzed for Analysis Status, and select Filter.

    1. You will now see only those samples from earlier exercises that have specimens with a status of Analyzed (i.e., they have been tested and the results approved in the lab).
    2. You filtered for Analyzed because these are typically the specimens that you will be editing and/or approving.
5. Highlight a sample to display that sample's specimens in the lower grid.
    1. Try sorting the lower grid by various column headers.
    2. Observe the various columns in the grid.
6. You are now at the place in MetaField where you can review, edit, and approve specimens:
    1. Inspect your specimen's test data.
    2. If you accept the results of that test, set its status to Complete.
    3. Optional: View and edit various specimen-related data by clicking the Edit, Edit Pick-Up, and Edit Check-In buttons.
7.Highlight the sample, and select the Edit icon for a particular specimen in the second grid. Enter report comments and close the dialog box.
8.Click the check box on the far left column to select all specimen that have had break results entered. Use the Set Change Status button to indicate the status of the specimens are Complete.
9.Select the completed specimen(s) again and click Finalize Specimen Report.
10.In the dialog box, select a Report Label and Office.
11.If you have an AgileStamp account, sign the report using your AgileStamp credentials, otherwise, uncheck the Digitally Sign Report checkbox.
12.Select the Finalize button to save the report.
13.Select the Open in Delivery button and find your new report in the Delivery module. You may see many reports in the report grid for this project.
14.Select the View PDF icon on the left to view the report.
15.Try printing or saving the report using the buttons on the PDF viewer. You can email the report by saving it and then attaching it to an email you create.
16.

Select the report you created, select Email. The recipients that were added to this report type in Project Administration will appear.

Optional: Add another recipient. Select the Add Recipient button. Fill in the required fields. Select Add.

17.Close the preview window.

...