Pending Field Action

Explanation

Density Tests

  • When a failing density test is saved in the system, a Pending Field Action is added to perform a retest. If a retest is later performed for the failing test, the Pending Field Action will be removed.

  • When creating a Work Order from this action:

    • Density Test - Retest Work Item will default

    • Technician will default to the Technician assigned to the failing density test

    • Notes for Technician will prepopulate with the type of test, test number, original Technician and tested date

    • All default values may be changed by the scheduler as necessary

  • When an Activity form has the "Density Test - Soil Nuclear Gauge" form setting, and requires a retest (Retest = Yes), the form will fall under Density Tests

Concrete / Grout / Mortar Samples

  • When a concrete, grout or mortar sample is saved in the system, a Pending Field Action is added to retrieve the sample

  • If there are field cure specimens, multiple pending field actions will be added (standard cure vs. field cure)

  • When creating a Work Order from this action:

    • C / G / M - Specimen Retrieval Work Item will default

    • Technician will default to the Technician assigned to the originating Sample record

    • Notes for Technician will prepopulate with sample type, Sample and Set numbers, original Technician and cast date

    • All default values may be changed by the scheduler as necessary

Activity Open Discrepancies

  • When an Activity is saved with a discrepancy, a Pending Field Action is added to review the discrepancy for resolution

    (Note: This assumes that the Form was configured to use Discrepancy management field settings. See Form Designer - Field Settings for more information) 

  • When creating a Work Order from this action:

    • Activity - Discrepancy Resolution Work Item will default

    • Technician will default to the Technician assigned to the originating Activity record

    • Notes for Technician will prepopulate with associated Group and Form name, Activity number for the discrepancy and original Technician

    • All default values may be changed by the scheduler as necessary

Sample Tracking Samples

  • When a Sample Tracking sample has been identified as needing to be retrieved, a Pending Field Action is added

  • When creating a Work Order from this action:

    • Sample Tracking - Specimen Retrieval Work Item will default

    • Technician will default to the Technician assigned to the originating Sample Tracking record

    • Notes for Technician will prepopulate with Sample Type, original Technician and Sample date

    • All default values may be changed by the scheduler as necessary

...